ISG Project 2018-19

The Ridge Steel team were extremely proud to be chosen as an ISG Plc delivery partner. As part of the 38 week project, we designed, fabricated, delivered and installed the steel and metal work for a number of ISG architectural metal work requirements including the chiller support steel work.

Get In Touch

ISG PROJECT 2018/19

RidgeSteel were contracted to carry out a number of steel and architectural metalwork packages for ISG for their new site at Imperial College, London, White City.  These included:

  • The chiller support steel work
  • Access ships ladders
  • Sprinkler pump room grating
  • Fan support steel work

The steel and metal work were first fabricated on site at RidgeSteel and then transported to the White City Site, where it was carefully lifted to the 12 & 13th floors of the building and installed up there.